The Construction Timeline

August 28, 2019: First day of school for students at our NEW school!
 
June 21, 2019: The old Jim Darcy School has been completely demolished to make room for the new playground.  Landscaping is the next step for the exterior, as a grant was received to plant trees all along Lincoln Rd.  On the interior, painting continues, and flooring, whiteboards, and fixtures are being installed.
October 18, 2018: Work continues on the new Jim Darcy School.  The third and final pod is being framed.  Roofing is taking place and classrooms are beginning to take shape.  On October 11th students and staff from Jim Darcy, as well as community members, celebrated a “Topping Out” ceremony as a beam with everyone’s signature was raised and placed by the ironworkers.
August 13, 2018: The past week at Jim Darcy was a busy one.  The south side of the center phase slab was poured and electrical and plumbing rough ins are continuing.  The east phase erection continues, and the CMU wall at the gym was completed!
July 31, 2018: During the past week a massive slab was poured at Bryant.  Foundation work is continuing to take place and steel beams are bring erected.
logo round.png

Bryant Elementary School

home of the panthers

Jim Darcy Elementary School

home of the mustangs

Jim Darcy Logo round.png

Our Community Partners

Throughout the design and construction process, architects and contractors met with past and current administration, teachers and specialists, students, parents, and community members.

HSD-logo.png
bottom of page